User
Write something
Unsecured 231kg Load Crushes Worker During Forklift Operation
During a routine loading operation, a forklift was being used to lift heavy electrical equipment onto a flatbed lorry. The equipment weighed approximately 231kg. The load was not secured to the forklift. A worker was acting as a spotter, standing close to the moving equipment. The load fell from the forklift and crushed the worker. The worker suffered severe brain and spinal injuries and now requires 24-hour care. A routine operation resulted in life-changing injuries. What Went Wrong ● Unsecured Load – The equipment was not positively restrained. ● No Lift Plan – The operation had not been properly planned or risk assessed. ● Unsafe Positioning – Workers were expected to physically steady heavy equipment. ● Poor Equipment Selection – A lorry-mounted crane was available but not used. ● Unsafe Routine – Repeatedly carrying out the task had created acceptance of an unsafe method. Key Lessons Learned ● A routine lift can still be dangerous. ● Never rely on workers to physically stabilise an unsecured heavy load. ● Select suitable lifting equipment before starting the operation. ● Keep personnel outside the line of fire. Safety Recommendations ● Prepare a suitable lifting plan and risk assessment. ● Secure loads using suitable, approved arrangements. ● Use available lifting points and appropriate equipment. ● Establish exclusion zones around loading activities. ● Never allow workers to stand where an unstable load could fall. ● Stop operations when the load cannot be safely controlled. Incident Source HSE prosecution report – 16 October 2026. The company was fined £4 million following a prosecution under Section 2(1) of the Health and Safety at Work etc. Act 1974. Regulatory Mapping ● LOLER Reg. 8 – Lifting operations must be properly planned, supervised and carried out safely. ● PUWER Reg. 4 – Work equipment must be suitable for the intended operation. ● PUWER Reg. 20 – Work equipment must be stabilised where necessary for health and safety. ● BS 7121 principles – Relevant good-practice lessons on planning, load control and keeping personnel clear, where applicable.
0
0
Unsecured 231kg Load Crushes Worker During Forklift Operation
Cantilevered Loading Platforms: Is the Platform Ready for the Lift?
Cantilevered loading platforms are commonly used on high-rise construction projects to receive materials from tower cranes. On 20 October 2026, the CPA published new industry guidance covering the safe selection, installation, operation, inspection and removal of these platforms. The lifting operation must consider more than the crane’s lifting capacity. What Can Go Wrong ● The platform’s permitted loading is not confirmed. ● Materials are placed incorrectly or concentrated in one area. ● The platform is used without confirmation that installation and inspections are complete. ● Crane operators and landing teams have unclear communication. ● Personnel enter dangerous positions during load landing. ● The AP and Temporary Works Coordinator fail to coordinate responsibilities. Key Lessons Learned ● The crane’s capacity does not determine the platform’s safe loading limit. ● The AP must consider the complete lifting arrangement, including the landing location. ● Temporary works approval and platform readiness must be confirmed before use. ● Material weight, positioning and loading sequence must be controlled. Safety Recommendations ● Confirm platform capacity and manufacturer requirements. ● Coordinate the lift plan with temporary works documentation. ● Verify installation, inspection and authorisation before loading. ● Establish safe access and exclusion zones. ● Agree communication between the crane operator and landing team. ● Plan platform installation and removal as controlled operations. Incident Source CPA Crane Interest Group and Tower Crane Interest Group – 20 October 2026. New industry guidance written by Conquip. This is a guidance-based safety study, not an accident investigation. Regulatory Mapping ● LOLER Reg. 8 – Safe planning and execution of crane lifting operations. ● PUWER Regs. 4 and 6 – Suitability and inspection of work equipment, where applicable. ● CDM 2015 Regs. 13 and 15 – Coordination and management of construction activities. ● BS 7121 principles – Safe lifting arrangements, landing areas and supervision.
0
0
Cantilevered Loading Platforms: Is the Platform Ready for the Lift?
Crane Delivery & Site Access: The AP’s Responsibility Starts Before the Crane Arrives
A mobile crane was scheduled to arrive on a busy construction site to carry out lifting operations. The lift plan had been prepared, the crane selected and the lifting accessories confirmed. However, the delivery and access arrangements had not been properly coordinated. When the crane arrived, the access route was partially blocked by parked vehicles and stored materials. There was insufficient space to manoeuvre, and the delivery trailers carrying counterweights and equipment had nowhere suitable to park. The crane was ready for work, but the site was not ready for the crane. What Went Wrong ● Site access had not been properly assessed. ● No suitable route had been confirmed for the crane and delivery trailers. ● Vehicle turning and manoeuvring space was insufficient. ● Counterweight delivery and unloading areas were not designated. ● Traffic management arrangements were unclear. ● Pedestrian routes conflicted with vehicle movements. ● Ground conditions along the access route had not been adequately assessed. ● Poor coordination between the AP, Site Manager and logistics team created unnecessary pressure. The AP’s Role in Crane Transportation The Appointed Person should ensure that the crane’s arrival, access, positioning and associated deliveries are properly considered within the lifting arrangements. This includes: ● Access Route – Confirm road widths, gradients, turning space, overhead restrictions and underground hazards. ● Ground Conditions – Check that access roads, temporary surfaces and hardstandings are suitable for the crane and transport vehicles. ● Crane Dimensions – Consider vehicle length, width, height, axle loads and any transport restrictions. ● Delivery Sequence – Coordinate the arrival of the crane, counterweights, mats, ballast and supporting equipment. ● Parking and Unloading – Identify suitable waiting, parking, assembly and unloading areas. ● Traffic Management – Coordinate with the Site Manager and logistics team to establish vehicle routes, pedestrian segregation and traffic marshal arrangements.
0
0
Crane Delivery & Site Access: The AP’s Responsibility Starts Before the Crane Arrives
In the Line of Fire: Worker Struck by a 4.5-Tonne Machine
During a machinery relocation operation, workers used a forklift to lift a 4.5-tonne machine so that skates could be positioned underneath it. The lifting arrangement was improvised, and the machine had already slipped from the forklift forks on two previous occasions. During another attempt, a worker positioned themselves underneath the suspended machine to secure a wheel. The machine slipped again, striking the worker and causing life-changing injuries. What Went Wrong The lifting operation was not properly planned. An unsuitable lifting arrangement was used. The machine had no dedicated lifting points. The load's stability and centre of gravity were not adequately assessed. Previous warning incidents were ignored. A worker entered the danger zone beneath the suspended load. The lifting method was not changed despite repeated failures. Key Lessons Learned Never position yourself in the line of fire. A suspended load can fall, rotate, slide or move unexpectedly. If a load slips once, the lifting operation must be stopped and reassessed. A near miss is a warning, not permission to try again. Safety Recommendations Ensure every lifting operation is properly planned. Use suitable lifting equipment and approved lifting arrangements. Confirm load weight, centre of gravity and stability. Establish effective exclusion zones. Never allow workers underneath an inadequately supported suspended load. Stop and investigate unexpected load movements. Use engineered methods to position skates or supports without exposing workers to crushing hazards. Ensure competent supervision throughout the operation. Incident Source Real UK lifting incident investigated by the HSE. The incident occurred in October 2023, and the prosecution outcome was published in January 2026. The company was fined £433,333, plus a victim surcharge, following breaches of LOLER Regulation 8. Regulatory Mapping ● LOLER Reg. 8 – Lifting operations must be properly planned, appropriately supervised and carried out safely.
0
0
In the Line of Fire: Worker Struck by a 4.5-Tonne Machine
Crane Unloading from the Road: When the Loading Area Becomes the Hazard
A crane was unloading a bundle of reinforcement mesh directly from a lorry positioned on a roadway. The photograph raises several serious concerns. There is no obvious segregated loading/unloading zone, a car is immediately alongside the operation, and a worker is positioned on the edge of the lorry bed while the load is suspended (ready to fall). There is also no clearly identifiable designated Slinger/Signaller visible controlling the lifting operation. In UK practice, this combination would require careful lifting, logistics, traffic and work-at-height controls. HSE guidance says loading/unloading should generally take place away from passing traffic, pedestrians and people not involved in the operation. What Went Wrong? The photograph suggests several potential failures: - No obvious segregated loading/unloading area. - Road traffic appears extremely close to the lifting operation. - No clearly identifiable Slinger/Signaller controlling the crane. - A worker is positioned at the edge of the lorry bed. - No visible collective fall protection around the working position. - Suspended reinforcement mesh is close to personnel. - No obvious exclusion/drop zone around the load. - The lifting operation and road traffic appear to be occupying the same space. HSE states that signallers directing cranes should be trained and competent and should work from a protected position. The Lorry Bed Is a Work-at-Height Risk One of the strongest lessons from this photograph isn’t actually the crane. Look at the worker. They appear to be sitting or slipping towards the edge of the vehicle while the load is being lifted. If workers must access a lorry bed, the risk of falling must be controlled. HSE recommends eliminating the need to climb onto vehicles where possible and, where access remains necessary, considering suitable access, walkways, guardrails or other appropriate safeguards depending on the operation. So the answer isn’t automatically “every lorry must have handrails.”
0
0
Crane Unloading from the Road: When the Loading Area Becomes the Hazard
1-30 of 36
powered by
Safe Lifting
skool.com/wolf-lifting-dynamics-9548
This community shares real lifting case studies, consultancy insights, and site-proven lessons covering cranes, supervision, planning, and execution.
Build your own community
Bring people together around your passion and get paid.
Powered by