Two project managers are working on resourcing their respective projects. Both project managers identified the same subject matter expert (SME) as being beneficial to their project. Project A is using a predictive approach and Project B is using an agile approach. To which project should the SME be allocated? 1. A.The SME should be assigned to Project A because project planning was based on the support of the SME. 2. B.The SME should be assigned to Project B because success in an agile project is determined by technical excellence. 3. C.The SME should be assigned to the project with the less experienced project manager to improve the likelihood of success. 4. D.The SME should be assigned to Project B because agile approaches prioritize flexibility and adaptability.