Two project managers are working on resourcing their respective projects. Both project managers identified the same subject matter expert (SME) as being beneficial to their project. Project A is using a predictive approach and Project B is using an agile approach.
To which project should the SME be allocated?
- A.The SME should be assigned to Project A because project planning was based on the support of the SME.
- B.The SME should be assigned to Project B because success in an agile project is determined by technical excellence.
- C.The SME should be assigned to the project with the less experienced project manager to improve the likelihood of success.
- D.The SME should be assigned to Project B because agile approaches prioritize flexibility and adaptability.