Quick update on house 1 of our current BRR project! 🛠️
The full rip-out, strip, and rubbish removal are complete. The electrical team has finished the first fix, and the plaster team is now in full swing. They’ve done a lot of prep work, including boarding, browning, and beading, and plastering has begun on the ground floor. Due to the extensive prep, the plastering will continue through next week, but we’re on track. The kitchen has been ordered and designed, and we’re gearing up for the next phase. The plasterwork should be wrapped up soon, and then it's on to the electricians and plumbers for the second fix 🔜 Excited to see this project coming together—will post another update next week