Delivery Arrives Before the Site Is Ready
A delivery vehicle arrived carrying materials that needed to be unloaded by crane.
The problem was simple:
The site wasn’t ready for the delivery.
The planned unloading area was occupied by stored materials, a concrete wagon was expected shortly, and another subcontractor had partially blocked the access route.
With the lorry already waiting, pressure developed to “just get it unloaded somewhere.”
The lifting operation was now being dictated by logistics rather than the lift plan.
What Went Wrong
  • Delivery timing was not coordinated with site activities.
  • The designated unloading/laydown area was unavailable.
  • Access routes were obstructed.
  • Materials already stored on site reduced available space.
  • Pressure to avoid delaying the delivery encouraged an alternative landing position.
  • Crane operations, deliveries and other moving plant were competing for the same area.
The Logistics Problem
Good lifting operations depend on good logistics.
Before the vehicle arrives, the site should know:
Where does it enter?
Where does it wait?
Where will it be unloaded?
Where will the materials be stored?
How will the vehicle leave?
If those questions are answered only when the lorry reaches the gate, the operation is already becoming reactive.
Key Lessons Learned
The crane should not become the solution to poor logistics planning.
Moving a load to an unplanned location can introduce new:
  • Ground-condition issues.
  • Crane-radius problems.
  • Pedestrian interfaces.
  • Vehicle conflicts.
  • Exclusion-zone problems.
  • Double handling later in the shift.
Sometimes delaying the delivery is safer than creating an improvised lifting operation.
Safety Recommendations
  • Use delivery booking/time slots.
  • Establish designated unloading and laydown areas.
  • Keep crane access and lifting zones clear.
  • Coordinate concrete wagons, pumps and major deliveries.
  • Confirm the unloading area before the vehicle enters site.
  • Prevent uncontrolled material storage in logistics routes.
  • Brief changes between logistics and lifting teams.
  • If the planned landing area is unavailable, stop and reassess before changing the lift.
Incident Source
Safety-learning scenario based on common construction logistics and lifting-interface problems.
Regulatory Mapping
● LOLER Reg. 8 – Lifting operations must be properly planned, appropriately supervised and carried out safely.
● CDM 2015 – Construction activities must be planned, managed, monitored and coordinated.
● Workplace transport principles – Vehicle and pedestrian movements require suitable routes and effective control.
● BS 7121 principles – Site conditions, crane positioning, landing areas and interfaces with other activities should be considered when planning lifting operations.
Key Point
A delivery arriving on site does not mean the site is ready to receive it.
Plan the gate.
Plan the route.
Plan the unloading area.
Plan the storage.
Most of the time, poor logistics eventually becomes somebody else’s problem.
Wolf Lifting Dynamics | www.wolflifting.uk | Case Study 142
0
0 comments
Vlad Lupu
4
Delivery Arrives Before the Site Is Ready
powered by
Safe Lifting
skool.com/wolf-lifting-dynamics-9548
This community shares real lifting case studies, consultancy insights, and site-proven lessons covering cranes, supervision, planning, and execution.
Build your own community
Bring people together around your passion and get paid.
Powered by