Five tower cranes operating simultaneously next to live public roads, lifting materials within a constrained site boundary. During slewing, the tower crane (TC1) hook-block extended beyond the designated site perimeter and over a public bus stop shelter. At the same time, a control fault occurred inside the crane cabin, where the joystick became stuck and the zoom/limitation system failed to respond as expected. The crane movement could not be immediately controlled, placing pedestrians and members of the public at risk outside the site boundary.
What Went Wrong
The lifting operation was carried out too close to a live public interface without adequate physical protection or secondary controls. Mechanical failure within the crane controls escalated the risk rapidly, and the exclusion zone did not extend far enough to protect third parties.
Key Lessons Learned
Public protection must extend beyond site boundaries
Crane failures can happen suddenly and without warning
Live roads and bus stops require enhanced planning and safeguards
Mapping Regulations
●LOLER 1998 – Regulation 4 (Strength and stability); Regulation 8 (Organisation of lifting operations, including protection of persons)
●PUWER 1998 – Regulation 4 (Suitability of work equipment); Regulation 5 (Maintenance)
●BS 7121-1 – Planning and control of lifting operations; protection of third parties and public interfaces
●BS 7121-2 / BS 7121-3 – Crane operational controls and safety systems (tower cranes)
●CDM 2015 – Management of risks to non-workers and the public