Useful free guide DCMA for P6 schedule assessment
I was involved in a project where the client required the schedule to pass the DCMA 14-Point Assessment.
The checks are simple, and they make weak programmes easy to spot, very useful also for claims management:
Missing logic under 5%
No leads, and lags kept under 5%
At least 90% finish-to-start relationships
Hard constraints under 5%
Activities and total float over 44 working days kept under 5%
No invalid dates, and no negative float left unexplained
Critical path test, CPLI and BEI to show whether the plan is realistic and being followed
Steve Montgomery at Ten Six has published a free eBook, An Introduction to the DCMA 14-Point Assessment, and I find it particularly well done. Each point is shown in Primavera P6 with practical examples, along with what to avoid and where to use judgement. No registration needed.
0
0 comments
Virgil Andrei
3
Useful free guide DCMA for P6 schedule assessment
powered by
Project Planning School
skool.com/projectplanning-7482
Grow your project planning & control career with expert training, assessments, tools, and a supportive global community
Build your own community
Bring people together around your passion and get paid.
Powered by