A project manager is leading a project that follows the company's predictive approach. The project manager discovers that the project is behind schedule and over budget because a key stakeholder has been submitting an unusually high number of change requests.
What should the project manager do to help the company achieve its desired project outcomes?
- A.Review the risk management plan to determine a mitigation plan.
- B.Use the contingency reserve to implement a fast-track activity.
- C.Review the change control process and implement improvements.
- D.Escalate the problem with the stakeholder to the project sponsor.