Why D is not the answer?
A project manager is leading a project that follows the company's predictive approach. The project manager discovers that the project is behind schedule and over budget because a key stakeholder has been submitting an unusually high number of change requests.
What should the project manager do to help the company achieve its desired project outcomes?
  1. A.Review the risk management plan to determine a mitigation plan.
  2. B.Use the contingency reserve to implement a fast-track activity. 
  3. C.Review the change control process and implement improvements.
  4. D.Escalate the problem with the stakeholder to the project sponsor.