During project initiation, the project manager learns that a key stakeholder will leave the project for a month to consult on another strategic project.
What should the project manager do first?
  1. A.Update the issue log and notify the other stakeholders.
  2. B.Ask the functional manager to provide a replacement while the stakeholder is unavailable.
  3. C.Interview the stakeholder to gather relevant information and expert judgment.
  4. D.Update the risk management plan to include the impact of the stakeholder's absence.