In the Simulator, there is a question as below. it says the right answer is Risk register and risk report.
but the The risk report is more of a summary tool, that summarizes overall risk status and trends, but it doesn’t list all individual risks in detail. It’s not the best source to check for new risks, while Risk Management Plan outlines how risk management activities will be structured and performed. It includes methodologies, roles and responsibilities, budgeting, timing, and categories of risk. It helps determine whether the newly identified risks fit within the existing framework or require updates to the plan. Thus, isn't the right answer should be Risk register and Risk management plan? M3Q6 A Project Manager identifies two new risks. These risks could impact a few key components. The Project Manager wants to reference additional information before presenting this new risk information.
To which sources should the Project Manager refer to check if these are new risks?
Risk register and risk report
Risk register and Risk management plan
Risk management plan and risk report
Issue log and risk report