Two homes delivered in Franklin County last week. Here's the full sequence from permit to CO. Delivery day is about the halfway point Leading up to delivery we've had to- - Soil Study and Survey the land - Secure Septic permit - Secure Building permit - Clear and grade the land - Pour footers - Coordinate with the energy provider to get in line for service connections Make sure you know your county timelines. In some areas this could be a couple days, in others this can be a few weeks, maybe even months. Delivery day- Home comes in on the truck. Usually takes about 2 days to properly set and install it. At this time you need to start walking interior and exterior and checking for any damages or issues with the home so you can get warranties and factory work started immediately. Then once it's set comes hooking up the utilities- Septic, well, plumbing, electric, HVAC. This is the phase where you're coordinating four or five different trades and any one of them can hold up the other four. Once the trades are complete, you get another inspection before moving on. Once you pass that inspection- we are in the final stretch Brick skirting, decks, porches, driveway, final grade, seed and straw. Then you get your CO and your power release. Two things people forget and both of them cost you buyers: 1. Termite treatment during construction. You need it for FHA and VA loan eligibility. If you skip it and try to come back later, you're fixing it under pressure with a buyer already under contract. 2. Engineer on standby to write a foundation certification. Also required for FHA and VA. Line that engineer up early. Do not wait until an underwriter asks for it. Miss either one and you just cut a big chunk of your buyer pool out of the deal. On a manufactured home, FHA and VA buyers are a huge part of your market. Questions on any of these phases, drop them below or bring them to the Thursday call at 10.