PMP Exam Questions
QUESTION 2
Also, this question for PMP Exam -
A project is facing a one-month delay, and the project manager realizes that a change request is necessary. The change control board (CCB) will review the change request at their next meeting, which is in two weeks. However, if the implementation of this change is delayed by two weeks, upcoming supply chain disruptions will cause a two-month delay to the project schedule.
What should the project manager do?
  1. A.Implement the change immediately to avoid the upcoming supply chain disruptions and the two-month delay.
  2. B.Revise the change request to incorporate the additional two-month delay due to upcoming supply chain disruptions.
  3. C.Meet with the sponsor and ask them to contact the CCB and request their immediate approval.
  4. D.Request that the CEO approve and implement the change to avoid the potential two-month delay.
1
2 comments
Pooja Roy Chaudhury
2
PMP Exam Questions
PMP
skool.com/pmp
Join our PMP hub to post questions, form study groups, and access free classes. Elevate your project management skills!
Leaderboard (30-day)
Powered by