One of the most challenging but exciting CRM projects I've worked on involved migrating 200K+ contacts and thousands of tags, automations, and external integrations (from make to n8n) from Keap CRM into GoHighLevel.
At first glance, a CRM migration can look simple, Export contacts, import contacts, and rebuild workflows.
In reality, it's way more complicated when you consider the amount of planning that goes in without you having to break communication with the existing customers.
When you're dealing with hundreds of thousands of contacts, years of historical data, thousands of tags, custom fields, automations, and existing customer journeys, one small mistake can affect thousands of records.
That experience taught me a few important lessons:
1. Don't migrate everything blindly.
Not every old tag, field, contact, or automation deserves to be carried into the new system. Some of the features are already outdated and need not to be moved to an improved system or process. Migration is also an opportunity to clean up the CRM, do away with unnecessary automations, and reduce the cost of running the new system.
2. Clean the data before migration.
Duplicate contacts, outdated information, inconsistent formatting, and unused fields can create bigger problems once they're inside the new CRM. There’s no need for you to move such information. If the old system presents an opportunity to clean up everything, then it’s best to do it right there.
3. Map your fields before moving anything.
You need to know exactly where every important piece of information is going in the new system. A successful migration isn't just about moving data. It's also about preserving its meaning. Failing to map the fields correctly will definitely end up breaking some important processes.
4. Audit your tags.
Thousands of tags can quickly become a mess if there isn't a clear structure, especially if they have been created over a look period. I look at what each tag represents, whether it's still being used, and how it connects to workflows and segmentation. Some tags, such as ones that were being used in old or seasonal marketing campaigns shouldn’t be moved along.
5. Rebuild automations carefully.
Moving the contacts is only one part of the project. You also need to understand what was happening to those contacts before the migration and recreate the important processes in the new CRM. Carefully go through all the automations, what they achieved and manually recreate them in the new system.
6. Test with sample records first.
Before migrating everything, test the process with a smaller group of contacts, check the fields, check the tags, check the workflows, check notifications, check pipelines, then scale. It will be a great injustice to months of work only to close down a working system for a non-functional one. Test over and over again.
7. Always have a validation plan.
After migration, the question shouldn't be, "Did the import finish?" It should be,
"Did the new CRM preserve the data, processes, and customer journeys we actually needed?" That's the difference between a CRM data transfer and a proper CRM migration.
I've also worked on migrating courses and affiliate programs from Teachable into GoHighLevel, which reinforced the same lesson: CRM migration is not primarily a data problem. It's a systems and process problem. The better you understand the business process before touching the data, the smoother the migration becomes.