Activity
Mon
Wed
Fri
Sun
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
What is this?
Less
More

Memberships

PMP

9.8k members • Free

16 contributions to PMP
Clarification on Escalation vs. Risk Register for External Threat
Hi all, I came across the following PMP scenario and I’m unsure about the correct approach according to PMBOK guidance: A project manager is tracking an infrastructure project that is dependent on a service provider. The service provider informed the project manager that some of the third-party components will no longer be manufactured or supported. Upon an initial review, this would significantly delay the schedule and increase the budget. Options:A. Escalate this issue to the project sponsor.B. Update the risk register.C. Convene a review with the team.D. Update the project status to reflect these findings. The official solution says A. Escalate to the sponsor, reasoning that it is an external threat beyond the PM’s control. My doubts: 1. The scenario does not explicitly state that the threat is beyond the PM’s authority. Couldn’t the PM first assess alternatives? 2. Option C (convene a review with the team) seems proactive to explore mitigation options. 3. Option B (update the risk register) is also important to formally document and monitor the risk. From a PMBOK perspective, would the first action always be escalation in this case, or should assessment and documentation (B or C) come first before escalating? I’d really appreciate any insights or references from PMBOK or real PMP exam reasoning. Thank you!
0
0
Seeking Advice on PMP Study Hall and Exam Preparation Challenges
Hello Skoll Community, I hope you're all doing well. I'm currently preparing for the PMP certification and using the PMP Study Hall for practice. I'm reaching out to see if anyone here has used the Study Hall and successfully taken the PMP certification. I've encountered some challenges with the expert-level questions in the Study Hall. They often seem more aligned with real-life scenarios rather than PMI's structured approach, and I've noticed that even the PMI Infinity Chat seems to get some of these expert questions wrong. Additionally, some questions reference articles or books written by professionals, rather than directly from the PMBOK Guide, which has made it a bit confusing for me to determine the best approach for my exam preparation. I've also taken the Andrew TIA Exams course and simulator, and I'm finding it challenging to reconcile the differences between these resources and the expert practice questions from the PMP Study Hall. This has added to my confusion about the best way to prepare for the exam. I would greatly appreciate any advice or insights you could share about your experience. Specifically, I'm interested in how you found the Study Hall's practice questions and how they aligned with the actual exam content. Do you find them beneficial for exam preparation, or do you recommend focusing more on questions that closely align with the PMBOK Guide? Thank you in advance for your help and guidance! Best regards,
Clarification on Using Management Reserve for Approved Scope Changes
Hi everyone, I came across a study question while preparing for the PMP exam, and I’d like your input to clarify a doubt: Scenario:A client requests a major scope change due to a change in the market environment, which will significantly add to the project cost. This change is approved through the change control process. Question: What should the project manager do to put the project on track?A. Reevaluate the scope baseline and impact on the project objectives.B. Use the management reserve to account for the schedule uncertainty.C. Monitor risks to ensure the effectiveness of the risk management process.D. Reevaluate the cost management plan to address the impact of the change. Provided solution: B. Use the management reserve. The rationale is that the market-driven change is an unforeseen, unknown-unknown event, and management reserves are intended to address such situations to keep the project on track. My reasoning / doubt: - The change has already been approved through change control, which means it is no longer “unforeseen” in the formal project plan. - Per PMBOK, management reserves are for unknown-unknowns that have not yet been planned or approved, and the PM usually needs sponsor approval to use them. - The textbook next step after an approved major scope change is typically to update the scope baseline and related plans (cost, schedule, quality) to reflect the change. - Using the management reserve before updating the baselines or getting formal approval may not align with PMI best practices. My question to the community: - Is B truly correct from a PMBOK/PMP perspective, even though the scope change is already approved? - Wouldn’t the PM need to update the scope baseline first and then, if needed, request management reserve usage? - How do you reconcile the guidance that management reserves are for unknown-unknowns with an approved change request? I’d really appreciate your insights — this seems like a subtle but important distinction that could affect how we answer PMP exam questions.
0
0
Clarifying PMP Exam Logic: Analyze Proposal First or Engage Stakeholders First?
Hi everyone 👋 I need help reconciling a difference I’ve noticed in PMP prep. Scenario: A team member proposes splitting a construction project into two phases, with an MVP in the first phase to reduce risk and cost overruns. The answer choices are: A. Conduct a feasibility study to assess risks and benefits. D. Discuss the proposal with the client and stakeholders to get their input. When I was studying for the PMP, I was taught that the correct exam logic is to do A first (feasibility study) before D (stakeholder discussion) so you don’t bring half-formed ideas to stakeholders. But I’ve come across a practice question where the official solution says D is correct (discuss with stakeholders right away), citing PMI’s emphasis on early stakeholder engagement. 👉 For the actual PMP exam, which order does PMI expect: A before D, or D first because stakeholder engagement comes before feasibility analysis? I’d really appreciate your insights so I can align my thinking with what the exam will test.
Question About Stakeholder Management vs. Resource Allocation – PMP Question Clarification
Hi everyone, I came across the following PMP-style question and wanted to get your thoughts: Question:A project manager is working on a complex project with many stakeholders and conflicting priorities. Senior management asked the project manager to avoid "noise" specifically for political projects. Although it is difficult to find resources for the project, what should the project manager do to ensure smooth progress of the project? Options:A. Apply "If you do something nice for me I'll do something nice for you."B. Be consistent with words and actions to avoid conflicts with the stakeholders.C. Utilize compliments to obtain resources, and cooperate toward mutual goals.D. Allocate the scarce resources efficiently to meet the needs of the project. Official solution: D My concern:The scenario mentions avoiding “noise” for political projects, which implies the PM needs to actively manage stakeholder relationships and influence, not just allocate scarce resources. Option D focuses only on resource allocation and doesn’t address the political/stakeholder sensitivity described. Option C, on the other hand, talks about cooperating toward mutual goals while influencing stakeholders (through compliments, rapport, etc.), which seems more aligned with both securing scarce resources and avoiding political conflict. I wanted to check: Is the official solution oversimplified? Could C also be considered a valid answer in the context of stakeholder management and influence, even though D is technically correct for resource allocation? Thanks for your insights!
0 likes • Aug 24
@Julie Khov thanks!
1-10 of 16
Beatriz Del pilar
2
7points to level up
@beatriz-del-pilar-1768
beatriz

Active 39d ago
Joined Jun 2, 2025
Powered by