A project manager is working with a team to develop work packages. The project manager noticed a gap in the requirements gathering where important points were missing, which would impact the project timeline.
What should the project manager do?
  1. A.Meet with the project sponsor to discuss canceling the project.
  2. B.Meet with the project sponsor and stakeholders to request a budget increase.
  3. C.Meet with the product manager to create a backlog with the missing requirements.
  4. D.Evaluate the impact, update the risk register, and present it to the stakeholders.